Back to articles

Case Study

Delivering our Full Data Centre Energy Stack in One Project

AVK's overhead crane at our assembly facility
Date
25 November 2026
Author
India Roberts
Read Time
8 min

Every data centre developer is asking the same question: how quickly can I get power? You’ve heard us say it before: our end-to-end power solutions can be the route to speed to power. Well right now, we’re working on a project that provides the concrete proof.

27

AVK PowerPods

50+

Rolls-Royce mtu generators

This project follows the steps we’ve taken to evolve and expand our capabilities to provide every part of a data centre’s energy lifecycle.  

On a large AI data centre campus in Europe we are delivering the complete AVK energy stack for the very first time. That means more than 50 gas Rolls-Royce mtu generators, modular energy systems (AVK PowerPods), switchgear, battery storage, and the controls that connect it all, supplied, assembled, tested, installed and commissioned by one team. It’s the biggest project we’ve ever taken on, and the clearest proof of how far we’ve come in expanding our capabilities to cover every part of a data centre lifecycle. This follows the launch of our modular solutions assembly facility in Haydock, North England, earlier this year, and in just a few months the facility has truly come into its own. Our full end-to-end solution is coming to life, and this is how we’re doing it.  

Our modular solutions assembly facility: Its progress and where we’re at now  

Our new facility in Haydock exists for one reason: to bring the building, assembly, and testing of our power solutions under one roof, in order to control quality and speed from start to finish. We announced the opening of the facility in April 2026, following the process of leasing and fitting out the interiors in the five to six months before. In this short and aggressive time-frame, we transformed the facility from a blank space to a branded warehouse capable of housing 23-25 PowerPods at one time with a total output of 100-120 PowerPods per year, with 140,000 sq ft of shop floor space, a 64-tonne high-lift crane, a fully installed busbar system, and a large-scale purpose-built environmental test laboratory designed to carry out full-load First of Kind testing to provide proof of every concept from design through to delivery. Complete with brand-new office spaces for both AVK teams and contractors’ teams, this facility took significant investment, and its investment that we’re already seeing the benefits of.  

The assembly facility received first orders just six months after the process to fit it out began, and we have already successfully delivered our 20th generator to site as part of this flagship project. Operations at our Haydock facility are well and truly underway. This progress, in just a few months, is an incredible turnaround. The facility is running at full capacity, and we already have appetite and demand that exceed the square footage of the warehouse, with another facility in the pipeline. Within the facility, we see a direct representation of how smoothly we can now deliver modular and containerised solutions independently and deliver a comprehensive offering combined with advantageous speed to power.  

A look inside: the full stack assembled and tested at Haydock 

Behind the headline numbers is a scope that we have never before delivered in one go. At Haydock, we’re working on the first phase of a high-profile project which is a 120mW AI data centre in Europe – delivering 50+ generators alongside 27 AVK PowerPods housing the switchgear and control room, two BESS systems, and the overall control system in its first phase. Its sister project, which we are also delivering, demands another large batch of generators, which results in AVK placing our largest cumulative order with Rolls-Royce for mtu gas engines to date. This will take the overall facility when completed to 300mW. This demonstrates the sheer scale of the project. This is the biggest project we have had on our books so far – the volume of mW we’re deploying is something we never could have imagined in AVK’s infancy, or even 5 years ago.   

What makes this project different is not only its size, but how complete it is. Every item on this list must work as part of one system: generators feeding switchgear, switchgear connected to battery storage, and controls bringing everything together. On most projects, that means several suppliers, several contractors and a handover at every step. Here one team is responsible, from the design through to the commissioning, so the customer has one partner to work with and one team accountable for the results. 

This project marks the first time we’ve delivered our containerised and modular solutions. We’re containerising the generators ourselves, and we’re doing so off-site in our facility, which has created a controlled and reliable environment. This has had concrete benefits – we have had full control over the system allowing for sophisticated time management and issue mitigation. This ensures a safe-guarded programme and seamless delivery. The containers have benefitted from an innovative design, with removable roofs that mean the engines will be lifted inside utilising the facility’s 64-tonne overhead crane. In some instances, this has enabled us to install the first fix containment in advance, ready for the coming engine delivery.  

We have been working to a regimented schedule – the site requires a delivery of two containerised generators at 8am every Tuesday morning. Over the course of an average week, we have two generators arriving, two in transit, and two being actively worked on in the facility. Delivering a project for a European data centre adds its own complexity – regulations are different and must be adhered to, as well as taking into account seismic environmental factors that demand an adapted design. Having catered to these requirements in a controlled environment has allowed us to ensure a higher quality of construction, with a rigorous testing process that is more reliable having been done off-site.  

AVK’s first PowerPods are in production as part of this project, with nine MV PowerPods currently in build and on track for delivery in mid-December. With generators, PowerPods, and more being built and tested under one roof, we can see how valuable Haydock really is. The assembly of the first PowerPods in AVK history marks an exciting occasion, and a controlled, secure facility allows us to ensure their quality whilst coinciding harmoniously with the timing of construction of the containerised generators in the same warehouse.  

There is another first here. For the first time, AVK is testing in-house before shipping. Inside the Haydock environmental test laboratory, equipment can be tested at full load before it leaves the building. Any issues are found and fixed in a controlled setting, not on a construction site, where time and options are limited. 

Testing gas generators at full load off-site for the first time 

In the opening of our assembly facility, another opportunity for innovation arose. We have designed a way to fully test the mtu gas powered generators to full load at the assembly facility rather than on-site. The facility isn’t near a natural gas main, meaning we had to find a temporary gas supply. We had a delivery of natural gas and pressurised it to a point where the generator could run for four hours with zero down time. Alongside AVK’s very own loadbanks which were simulating the same mW of power needed to run the generator as on-site, the continuous supply of natural gas allowed us to reliably test the efficiency and resilience of the generator in a controlled setting. This gives reassurance to the customer, as well as positioning AVK as a truly innovative problem solver – we will always find ways to enhance our offering and ease a customers’ experience. 

Here we see clearly the critical role that our assembly facility plays. The majority of the physical infrastructure assets are assembled and tested in the facility, so much so that our team is confident in the performance of the asset once it is delivered to site. This means the full stack arrives on site already tested. 

Standby technology at Prime scale  

With how extensive this power solution is, it’s not an average project. The scope and complexity of this programme means that if needed, the amount of power deployed could be utilised as a prime power source. The system is built as standby, but has the complexity of a microgrid, even though that’s not its primary purpose. We’re the only company capable of providing a solution this complex to this scale, with our experience in deploying a live microgrid providing on-site power to a data centre in Dublin as a proof point.  

With the reliability of the fuel selected and the mW included within this system, there is no reason why the data centre wouldn’t be able to be run exclusively from these engines if it needed to. Grid connection delays are an infamous struggle for the industry, but we’re providing the solution.  

 

A scope that paves the way for the future  

This is a foundational project that paves the way for AVK Capital. AVK Capital is designed to offer data centre developers the full power stack, funded by our financial entity. This project, providing every touchpoint in our value stack for data centre power, is a perfect example of the extensive offering provided via this avenue. From what we have achieved in this project, we’re providing a real, achievable example of our Power of ONE approach – all power infrastructure, from design to delivery, end-to-end, under one expert power partner. Our facility in Haydock is crucial for this process – we control quality, coordinate project timelines, and provide speed to power with the addition of this factory into our processes.  

A flagship project for our end-to-end power solutions, a data centre developer can look at our success in this deployment, in the utilisation of our high-class facility in Haydock, and be confident in the comprehensive solution they will receive – funded, owned, and operated by AVK. 

For the data centre developers who follow, it is the proof that it can be done.